Pour Day Planner
Get an hour-by-hour pour timeline with TM intervals, checkpoints, and equipment requirements.
60 sec
// Live Tool
Inputs
8–12 m³/hr
5–8 m³/hr
15–25 m³/hr
25–40 m³/hr
10–15 m³/hr
Live Output
Pour Duration
1 hr 34 min
Start 8:00 AM → Estimated finish 9:34 AM
TMs NeededGOOD
9
10-min intervals at 6 m³ each.
Cube SamplesGOOD
12
Per IS 456:2000 Table 11.
WorkersGOOD
16
Crew sized to placement rate.
VibratorsGOOD
4+2
4 working + 2 standby.
Hour-by-Hour Timeline
- 7:30 AMFirst TM arrives, slump test, initial cube samples
- 8:00 AMPour starts (pump — boom)
- 8:23 AM25% complete (12.5 m³)
- 8:47 AM50% complete — water supply check
- 9:10 AM75% complete (37.5 m³)
- 9:34 AMPour completes (50.0 m³)
- 9:49 AMFinal cube samples cast
- 10:04 AMBegin curing setup (within 2 hr of placement)
// Interpretation
What this means
// NOTE · Pour plan summary
Your 50 m³ pour with pump — boom will take approximately 1 hr 34 min starting at 8:00 AM. You'll need 9 TMs at 10-minute intervals. Critical: have 12 cube molds ready and 4+2 vibrators on site.
// CRITICAL · Critical reminders
- All TMs must arrive within 90 minutes of batching.
- Slump test on every TM at site — don't skip.
- Cube samples cast as concrete arrives, not at the end.
- Engineer-in-charge present throughout the pour.
- Begin curing within 2 hours of placement.
- Plan for delays — keep a backup placement plan and joint location ready.
// Context
When to use this
// What is this
Pour day is the most critical day of construction. Poor planning = cold joints, honeycombing, missed cube samples, rushed placement. This tool gives you a calibrated plan with timing, equipment, and crew sizing.
// When to use it
Use 24–48 hours before the pour to brief crew, confirm TM scheduling with dispatch, and stage equipment and cube molds.