    Tech Park, LEED Gold Certified

    ORR North, Bangalore · Anonymized (multinational developer) · 2024
    Volume
    6,200 m³
    Grades
    M40, M30
    Duration
    12 months
    Special
    Low-Carbon, LEED, EPD

    Project overview

    A 4-block tech park targeting LEED Gold required low-embodied-carbon concrete with verified EPDs. Alpha Green delivered 6,200 m³ across M30 and M40 with 50% GGBS replacement, achieving a 45% reduction in embodied CO₂ versus the regional baseline. Full EPD documentation supported the LEED MR Credit 5 submission.

    Sustainability-led commercial campus; LEED v4 BD+C scorecard; client procurement required EPD evidence.

    The challenge

    Low-carbon spec with LEED-grade documentation.

    • 50% SCM replacement without compromising 28d strength
    • EPD per ISO 14025 for every grade
    • Strength gain still meeting fast slab cycle
    • Documentation chain auditable by LEED reviewer

    The solution

    Alpha Green mix with 50% GGBS, third-party verified EPD per grade.

    • 50% GGBS replacement, M30 and M40
    • ISO 14025 EPDs per grade, third-party verified
    • Extended curing protocol (10 days)
    • Audit-ready batch tickets and CO2 ledger per delivery

    Execution detail

    6,200 m³ delivered; full EPD chain submitted with LEED docs.

    • Embodied CO2 reduction: 45% vs baseline
    • M40 28-day mean: 45.6 MPa
    • Slab cycle held at 8 days with extended curing
    • 100% deliveries with EPD-tagged batch tickets

    The result

    LEED Gold awarded; MR Credit 5 evidence accepted on first review.

    LEED Gold (BD+C)

    "The EPDs landed without a single follow-up question from the LEED reviewer."

    — Sustainability Lead (anonymized)

    Technical specifications

    GradeCement (kg/m³)SCMw/cSlump
    M40190GGBS 1900.4125±20
    M30170GGBS 1700.45100±20

    QC: EPD per grade, per-load CO2 ledger

    Products used

    Have a project like this?

    Talk to our technical team about your mix, schedule, and logistics.

    Talk About Your Project
    // Your privacy

    We use cookies to make this site work better.

    Essential cookies are always on. Analytics and marketing cookies are off by default — turn them on if you'd like to help us improve. See our Cookie Policy and Privacy Policy.