    Edition: 1st EditionYear: 1975Pages: 20

    About this code

    Practical recommendations for concreting in hot weather — temperature control, scheduling, ice use, curing protection. Critical for Bangalore April-October.

    Key sections

    1. 01Effects of hot weather
    2. 02Temperature limits
    3. 03Materials handling
    4. 04Placement and curing

    Critical clauses

    Clause 4.0Temperature Limits

    Concrete temp at placement preferably <= 30°C, max 40°C.

    In practiceUse chilled water or ice when ambient > 35°C.

    Clause 5.0Material Cooling

    Cool aggregates and water; shade stockpiles.

    In practiceEach 1°C drop in concrete = ~4°C in aggregate.

    Clause 6.0Curing

    Continuous moisture for first 24 hours critical.

    In practiceWet hessian + sprinkling, never let it dry.

    Practical implications

    For specifiers

    Reference for summer specs.

    For suppliers

    Schedule early/night pours.

    For executors

    Plan curing logistics.

    FAQs

    What temp triggers hot weather measures?

    Ambient > 35°C or concrete > 30°C.

    // Need full code text?

    Purchase the official Bureau of Indian Standards publication for the complete, legally-binding text.

    Open BIS Portal

    This summary is for quick reference. For legal compliance and project specification, refer to the official BIS publication. Standards are periodically updated; verify current edition with BIS before reliance.

    // Your privacy

    We use cookies to make this site work better.

    Essential cookies are always on. Analytics and marketing cookies are off by default — turn them on if you'd like to help us improve. See our Cookie Policy and Privacy Policy.