    Construction Practice

    IS 4926:2003

    Ready-Mixed Concrete - Code of Practice

    Edition: 2nd RevisionYear: 2003Pages: 24

    About this code

    Code of practice for ordering, manufacture, transport, and acceptance of ready-mixed concrete. The reference standard for RMC operations in India.

    Key sections

    1. 01Definitions
    2. 02Ordering
    3. 03Manufacture and delivery
    4. 04Acceptance criteria
    5. 05QC requirements

    Critical clauses

    Clause 5.0Ordering

    Specify grade, slump, max aggregate, exposure, additional requirements.

    In practiceUse a structured order form to avoid errors.

    Clause 6.0Delivery Time

    Within 90 min of batching, 30 min of arrival.

    In practicePlan trip times — Bangalore traffic kills this.

    Clause 7.0Acceptance

    Per IS 456 strength, slump within tolerance.

    In practiceReject if slump > +25mm or < -25mm of design.

    Practical implications

    For specifiers

    Use this for RMC tender clauses.

    For suppliers

    This is your operating manual.

    For executors

    Reject loads outside spec.

    FAQs

    Can water be added at site?

    Only if total w/c stays within design — and only by RMC supervisor.

    // Need full code text?

    Purchase the official Bureau of Indian Standards publication for the complete, legally-binding text.

    Open BIS Portal

    This summary is for quick reference. For legal compliance and project specification, refer to the official BIS publication. Standards are periodically updated; verify current edition with BIS before reliance.

    // Your privacy

    We use cookies to make this site work better.

    Essential cookies are always on. Analytics and marketing cookies are off by default — turn them on if you'd like to help us improve. See our Cookie Policy and Privacy Policy.