    Construction Practice

    IS 14687:1999

    Falsework for Concrete Structures - Guidelines

    Edition: 1st EditionYear: 1999Pages: 28

    About this code

    Guidelines for design, erection, and removal of formwork and falsework. Covers loads, materials, safety, and stripping times.

    Key sections

    1. 01Materials
    2. 02Design loads
    3. 03Erection
    4. 04Stripping times
    5. 05Safety

    Critical clauses

    Clause 7.0Stripping Time

    Sides 24h, soffits 7-21d depending on span.

    In practiceRead with IS 456 clause 11.3.

    Clause 8.0Safety

    Bracing, base plates, inspection schedule.

    In practiceFalsework collapse = catastrophic.

    Practical implications

    For specifiers

    Reference for falsework specs.

    For suppliers

    N/A — contractor scope.

    For executors

    Train crews on stripping schedule.

    FAQs

    When can soffit forms be removed?

    Slab spans <4.5m: 7 days; beam soffits up to 6m: 14 days; over 6m: 21 days (OPC).

    // Need full code text?

    Purchase the official Bureau of Indian Standards publication for the complete, legally-binding text.

    Open BIS Portal

    This summary is for quick reference. For legal compliance and project specification, refer to the official BIS publication. Standards are periodically updated; verify current edition with BIS before reliance.

    // Your privacy

    We use cookies to make this site work better.

    Essential cookies are always on. Analytics and marketing cookies are off by default — turn them on if you'd like to help us improve. See our Cookie Policy and Privacy Policy.